Most recent Village paving information

The first phase of the Hot Springs Village Property Owners' Association road paving program will continue through July 6. The contractor is Cranford Construction of North Little Rock.

Plans are underway to pave the following roads on Monday, July 2: Malaga Way, Alcanara Lane, Matamoroe Way, Durango Way and Bahia Lane.

The crew will not work July 3-4. Plans are underway to pave the following roads on Thursday, July 5: North Pego Way, Navia Lane, Grado Lane, Cabra Lane and Empinado Lane.

The POA will distribute flyers to residents in the affected areas in advance of the paving. Please observe all posted signs and avoid roads to be paved, if possible.

Weather and contractor availability determine the paving schedule. All streets and dates are subject to change.

Please contact the Public Works Department at 922-5524 for the most up to date changes.