Wednesday, July 24, 2013

Resurfacing schedule

The Hot Springs Village Street Resurfacing program is currently underway. Martin Marietta paving crews are resurfacing the following streets the week of July 23-26:

Wednesday, July 24 - Cordero Lane, Emanuel Circle, Emperado Way, Ensenada Lane, La Vista Lane & Matamoroe Way

Thursday, July 25 - Barcelona Rd. (La Coruna-Calella), Alcantara Lane, Lonjeta Lane & Sandalo Lane

Friday, July 26 - DeSoto Marina Rd., Los Lago Way, Plana Place

Flyers will be distributed to residents in the affected areas in advance of the paving. Please observe all posted signs and avoid roads to be paved, if possible.

Schedule is subject to change. For the latest road resurfacing information, click the “Sign Up for POA E-News” button on the http://www.hsvpoa.org homepage and sign up for email blasts or contact the public works department at 922-5524 or 922-5528.