Village paving schedule


The first phase of the Hot Springs Village Property Owners' Association Road Paving Program will continue through July 6. The contractor is Cranford Construction of North Little Rock.

Plans are underway to pave the following roads by Friday, June 29: Alicante Road, Alba Lane, Alba Circle, Plana Place, North Badalona Drive, Badalona Circle, Badalona Lane, Cantalejo Lane and Tarrase Lane.

Next week, the paving crew will work Monday, July 2; Thursday, July 5; and Friday, July 6. Plans are underway to pave the following roads by July 6: Malaga Way, Alcanara Lane, Matamoroe Way, Durango Way and Behaira Lane.

The crew will return later in the summer to finish paving.

The POA will distribute flyers to residents in the affected areas in advance of the paving. Please observe all posted signs and avoid roads to be paved, if possible.

Weather and contractor availability determine the paving schedule. All streets and dates are subject to change.