Search This Blog

Monday, February 14, 2011

2011 POA golf project list

The following list contains projects outside the scope of large scale "capital" projects such as course or club house renovations. These projects are identified and prioritized as to availability of labor, funds, and optimum weather conditions for each project. Many will be accomplished by the maintenance crew at the individual courses, some however need the help of the golf construction crew, those will be recorded. Following is the list for 2011 – any that are not accomplished in the next calendar year will take priority in 2012. The projects are listed by course and are not prioritized here. * * denotes need for construction crew.
Desoto Golf Maintenance:
• Remove silt from around the pump house near 6 green. Major project (complete)
• Cut and remove 37 dead trees – (winter ) * mostly complete 12 need professional
• Stump grinding for these and others from 2010 – ( spring)
• Add drainage lines in low spots #1 fairway – (summer) * *
• Renovate Bunker including new drainage (greenside) hole 13 * *
• Renovate Bunker including new drainage (greenside) hole 14 * *
• Renovate cart path hole #10 * * (Dec. ) * also number 7. Temp fix till concrete
• Clean Gabions in drainage way between holes 6 and 7 * *
• Clean ditches remainder of course
• Painted Halfway houses – interior (complete)
• Renovate all signs – yardage poles – tee markers. (Complete)
Desoto Club House:
• New roof shingles on cart barn (contracted)
Cortez Golf Maintenance:
• Removal of shade trees behind # 6 tee to promote sunlight to the area (winter) complete
• Removal of trees to promote sunlight to 14 tee to promote turf growth ( winter) * *
• Remove some trees blocking morning sun to 14 green to promote turf growth complete
• Draining of pond on #4 to "bake" the banks to help alleviate algae growth in pond.
This will take most of the winter, pond will be refilled in spring and fountain returned, in progress
• Retrench ditch on hole 15 to help with drainage. (winter) complete
• Install drain line in constant wet area by the putting green, in progress
• Add irrigation heads to dry areas on holes 11 and 12 * *
• Install drainage to wet area hole #12 * *
• Install drain line to wet area in #7 fairway * * summer
• Remove brush from dam on # 8 (winter) complete
• Remove brush on hillside # 7 tee (winter) complete
• Remove brush on hillside # 2 forward tee (winter)
• Limb trees (course wide) to promote sunlight (winter) in progress 50% complete
• Remove and stump 45 dead trees around the course (winter) in progress 80% done
• Paint signs – distance poles – accessories complete
Coronado Golf Maintenance:
• Continue to plug weak areas of greens–top dress and have them back 100% by April
• Cut 50 dead trees around course – 90% complete
• Plugging greens 75% complete
• Install drainage lines in wet spots # 1 fairway * *
• Install drainage lines in wet spots # 4 fairway * *
• Install drainage from catch basins down the fairway (complete) * *
• Add a catch basin and lateral lines for drainage # 8 fairway * *
• Install lateral lines for additional drainage # 10 fairway * *
• Replace culvert under cart path and add drainage to 16 fairway * *
• Add additional drainage to # 17 fairway * *
• Renovate both course restrooms – * * help also from building maintenance
This list is very aggressive and all may not be accomplished this year.
Coronado Club House:
• Renovate both men’s and women’s restrooms inside the clubhouse (spring)
• Replace and widen the cart path from the cart barn to parking lot * *
Magellan Golf Maintenance:
• Repair greens drainage # 5 green (winter)
• Clean out ditch along # 5 fairway (winter)
• Cut approximately 45 dead trees around course (winter) in progress 50 %
• Replace rusted catch basin # 8 fairway – * * summer
• Replace rusted catch basin # 15 fairway – * * summer
• Install new drainage # 15 fairway * * summer
• Clean out silt from ditches # 4 behind green and # 5 tee * * winter
• Level high areas along cart paths for better drainage across path. 30% complete
• Replace rusted overflow pipe #12 pond. * * (summer)
• Install new drain line across fairway in front of # 10 green * *
• Level forward tee # 5 – * * (summer)
• Convert the following bunkers from sand to grass depressions: (summer)
# 9 first fairway bunker
# 10 greenside bunker
# 5 greenside bunker
# 14 greenside bunker
# 13 first fairway bunker
# 15 right fairway bunker
Reduce the size of # 9 greenside bunker
All will need the help of the construction crew and what we do not get to in will be carried forward.
•Clean all greens drain lines complete
• Clean underbrush around course 75% complete - major project
• Renovate all tee markers – ball washers – signs – poles coolers – bag racks - complete
Magellan Golf Shop:
• Replace carpet in golf shop – hallway and restrooms – winter/spring
Balboa Golf Maintenance:
• Add lateral irrigation heads to left side of 5 fairway where it stay dry – winter
• Reconstruct drain and drain line 13 fairway by 100 yd. marker winter ** complete
• Install drain line in front of 18 green. winter ** complete
• Repair cart path next to # 6 tee – winter
• Repair cart path next to 15 tee – winter
• Replace railroad ties by cart path around 16 and 17 greens with stone – winter
• Cut down 47 trees course wide and stump - winter ½ way complete
• Limb around entire course – winter ½ way complete
• Greenside bunker # 13 renovate bunker
• Replace handrails around restroom/ ½ way house 15 tee ** complete
• Clean ditches – 2 – 6 – 16 and pond on driving range ** complete
Balboa Club House:
• Renovate all interior restrooms
Isabella Golf Maintenance:
• Replace 5 sections of cart paths various places around the course – * *
• Drainage ditch # 1 (SM) cleaned out winter * * complete
• Drainage ditch # 9 (SM) cleaned out – winter * *
• Install new drain lines # 6 fairway Nina – summer * *
• Install new drain line # 5 fairway Pinta – summer * *
• Remove all dead trees and stumps approx. 39 – winter 90% complete
• Cart paths edged ** complete
• All signs – tee markers – poles – ball washers renovated **complete
Isabella Club House:
• Replace Patio Furniture spring
Granada Golf Maintenance:
• Take out "volunteer creek willows" and clean creek 12 13 winter ** 90 % complete
• Repair cart path # 4 - * *
• Take out 15 dead trees around the course and stumps – winter ** complete
• Clean out area between 4 and 5 – winter * *
• Replace sand in # 5 left front bunker spring ** complete
• Replace sand in # 9 left front bunker spring ** complete
• Replace sand in # 8 back greenside bunker spring ** complete
• Convert waste area on #10 to grass depression
• Sod # 3 by cart trail from winter kill of 2009 – summer
• Halfway houses and driving range restrooms painted interior ** complete
Granada Restaurant:
• Replace Patio Furniture – spring
Ponce Golf Maintenance:
• Fairway drainage project continues on the following holes: 3, 5, 10, 12, 18 – finish entire project by end of summer * *
• Bunker renovations on the following holes:1, 2, 6, 7, 10, 11, 12, 16, 17, 18
• Possible replacement of the culvert under 14 fairway (deteriorating) * *
• Reshape and sod # 12 black tee - summer
• Remove 75+ dead trees - 90% complete this is a major project
• Cutting tree limbs around the course for light and drainage – 90% complete
• Drain Lines cleaned and ditch’s cleaned complete
• During bad weather – have been helping renovation in restaurant ** complete
• Painting trim on outside of halfway houses ** complete
• Paint interior of halfway houses - winter
Ponce Golf Shop and Restaurant:
• Renovate HVAC system (restaurant) winter, in progress
• New ceiling tiles (restaurant) winter, in progress
• New flooring – winter – restaurant – golf shop – hallway in progress
• New patio furniture –spring

No comments:

Post a Comment